Project Name: CEG Fiata School Project

Project Location: Fiata, Lomé Togo
Project Start Date: May 21, 2021 | Project End Date: August 21, 2021
Project Status: Project completed. handed over to the local government authorities
Project Budget: The budget is currently being computed. 
Project Partners / Collaborations: BASIA, CoAfrica , and LDS Charities

Challenges / Opportunity:

  • Insufficient classrooms for the students and the staff. 
  • The existing classrooms are grossly dilapidated. 
  • Many school-age children could not attend because of a lack of classrooms.

Final Project Deliverables:

  • A block of 4 classrooms, 
  • two units of toilet facilities for boys and girls, 
  • borehole, 
  • overhead water tank, and
  •  school supplies.

Project Impact:

Three hundred twenty (320) students were already shortlisted to use the newly constructed classrooms facilities.